Ormond Zone Substation transformer replacement

The existing Number 2 transformer at our Ormond Zone substation has reached its end of life. To ensure the continuing supply of electricity to the area, we’re undertaking a $3.2m project to replace it, with the new Number 2 transformer scheduled to be delivered in February 2022. Installation is scheduled to be completed by June 2022.